Flexi House - Show Home
Prototype & Proof of Concept build
4 Bedroom, 2 bathroom workers accomodation
Stage 1: 1 Bedroom, 2 bathrooms
Stage 2: Add up to 3 bedrooms
Footprint: 67m2
Location: Mount Pisa, Central Otago
Built: May - Aug 2022
Manufacturing: 7 weeks
Assembly time: 13hrs
Onsite Build: 6 weeks
Total build time: 13 weeks (3 months)